Platform Frontage Walls for Kiwirail

By October 15, 2020 Case Studies, Newsroom

The first of nearly 200 Type 1 KiwiRail Platform Frontage Walls were recently placed in Trentham with 910 pavers to complete the package.

These came from our Palmerston North Manufacturing Plant and our Pokeno Plant are busy manufacturing further supply for placement in Hamilton and Huntly. It’s good to see investment going into our train lines.